When projects and staff are imported into Synergy, it will default to the login users primary office. It is not possible to import to a secondary office. You will need to change the primary office of the staff member if you want to do a bulk import to another office - see the example below. The project financials will inherit the project's office and there will be no effect when importing contacts.
EXAMPLE: If your System administrator is part of the Melbourne office, any staff or project imported using Excel imports will be logged as part of the Melbourne office. If the imports are related to the Sydney office, the system administrator- in Staff > Details, will need to change their primary office to the Sydney office. Any new project or staff imported will be linked to the Sydney office.
Read about how to do this in Data import.